FUMC BUILDING TIMELINE AND HISTORY OF APPROVALS

 

 

February 1999             Vision Team begins site assessment of church property, Richard Dorton, chairperson

 

February 2002             Home meetings for purpose of defining ministry needs

 

February 2002             Charge Conference approval to develop Building Task Force

Approval to hire professional consultants – Partners selected

 

September 2002           Evaluation of programming needs and site analysis –

                                                Christian Life Center and Sanctuary were planned objectives

 

May 2003                    Andover loan acquired; multiple site church postulated

 

September 2003           Wednesday Family meeting held to provide info on expansion and parking concerns

 

March 2004                 Sanctuary made first priority

 

March 2004                 Season of Listening - congregational and home meetings

 

September 2004           Partners report of Site Analysis with Sanctuary proposal on High and Mill St. lot

                                    Home meetings

 

January 2005                Approval of West Chapel and Gathering Hall renovations

                                    Approval of Feasibility study for new sanctuary

 

September 2005           Series of Congregational meetings to report sanctuary plans in progress

 

December 2005           Expansion of present sanctuary reported as inadequate and too expensive

 

February 2006             Church Conference for purchase of CMW property on High and Broadway at $2,200,000

                                                88% approval (193 yes vs 28 no)

 

May 2006                    Andover Campus Development plan presented and accepted

                                    Generis selected as our Capital Campaign consultants

 

June 2006                    First Family Strategic Planning Event  with over 150 people present

1.      Prioritized building needs to address space issues for children, youth, ground level fellowship hall, offices, prayer, and worship.

2.      Andover plan as a satellite campus approved

 

July 2006                     Approval of change in worship times to help equalize attendance in two worship services

                                    Offerings approved as third service alternative

                                    Capital Campaign approved.  The following priorities were given:

1.      Pay off existing debt

2.      Build fellowship hall, education space, remodel current fellowship hall and music suite

3.      Worship facility at Andover campus   (Recreational hall, too??)

4.      Sanctuary at downtown campus

Approval was given to develop Andover building plan

 

November 2006           Plan A of Partners approved at Charge Conference to include purchase of 327 S. Upper

 

December 2006           Church Conference approves purchase of 327 S. Upper at $650,000

                                                (90 yes vs 9 no)

 

January 2007                High St. and Broadway property was taken off of priority list as debt needing to be paid

 

February 2007             Charge Conference approves establishment of FUMC Realty Co.

 

May 2007                    Generations campaign completed with $4.6 million in pledges reported

 

June 2007                    Generations pledges now total over $4.7 million

Timeline for construction presented, beginning from present until Phase 3 completion

in June 2009

Design and Development/Construction Documents (Phase I) approved to begin with

necessary reviews and permitting as needed

Building Team, along with other key leadership, was asked to work with Partners in

developing a financing plan

                                    Church offices approved to be moved to Rokeby Hall                          

                                    Andover Renovation approved ($199,000)

 

September 2007           Admin. Council recommends $1,239,428.30 to be paid from Capital Campaign funds collected (for Office/Slayton Chapel renovation, West Chapel renovation, Partners consulting fees, Generis consulting fees, Capital Campaign expenses, Andover Master Plan, Andover Renovation, Rokeby Hall Addition, Broadway Loan, and a line of credit)

 

November 2007           Charge Conference increased Rokeby Hall expense line by an additional $100,000 to include a basement (not to exceed $450,000)

 

July 2008                     Rokeby Hall expansion and renovation completed.  Staff office moved from Old Parsonage to Rokeby Hall.